Project Details

• Installation of underground electrical reticulation
• Installation of 10 x 12m light towers
• Installation of 4 x 15m light towers
• Installation of modified head frames to suit additional light fittings on the light towers
• Modifications to concrete footings to suit new light arrangement on the light towers
• Installation of 120 x 400watt LED light fittings
• Installation of 4 x 2kW Disano Olympic light fittings onto Court 9
• Replaced 40 x metal halide lamps in the Ken Rosewall court
• Modifications to existing distribution boards
• Aiming/focusing & illumination testing



Electrical Package Consists of:

• Electrical Infrastructure
• LED Lighting Upgrade
• Sports Lighting
• Lighting Control / Automation
• Civil Works